Kevin's scatter build thread

Roof work today. Glad I don't do roofs for a living.

20220212_102026.jpg
20220212_102039.jpg
20220212_160514.jpg
 
More progress. The goal is inspections on Tuesday and drywall next weekend. If my windows show up that is
20220218_165220.jpg
20220218_165237.jpg
20220218_165306.jpg
20220218_165428.jpg
20220218_165220.jpg
20220218_165237.jpg
20220218_165306.jpg
20220218_165428.jpg
 
All wired up. Next are inspections, (waiting on one now). My son and I did this last night. I powered up the building so I was able to use temp lights
20220228_073547.jpg
20220228_073525.jpg
20220228_073511.jpg
20220228_073446.jpg
20220228_073438.jpg
 
What do you call an Electrician doing soffit work? FIRED!!! :lol:

Actually it came out pretty good for my first time ever doing it. Pretty satisfying as well. I have to leave the exposed part like this until it is inspected. Finished with all the little extras and got 3 pieces of insulation up before it went dark on me. I could have run temp lights but I'm beat and I don't want to start overdoing it now. I had intended drywall hanging this weekend but it looks like a Monday task.
20220305_160048.jpg
20220305_160104.jpg
 
Last edited:
coming together
I really need my contractor buddy to bring his trailer over so I can get rid of this construction garbage. If I put a dumpster or even a dumpster bag in front, the neighborhood will load it up on me.

I ordered my flooring and once drywall is complete, its game on. I am still waiting on the windows unfortunately; however, I will board them up and keep going. AC mini split comes in next week. I prewired low voltage lighting for cabinets , cameras and alarm.
 
Windows
Poo doo!!

Took weeks to get them and a pain to install but I did it. The white around Windows and door is a sealant required by local code enforcement. Kinda like spreading marshmallow fluff. I rented a drywall lift for the ceiling and my son and I did that.

Weekend goals, -finish drywall so I can begin drywall finishing

AC goes in next week.
20220325_184944.jpg
20220325_184805.jpg
20220325_184826.jpg
 
Drywall-check
Painting- This weekend
AC was supposed to have already been installed but typical delays. Scheduled for Monday
Flooring starts Monday as well.

Then I have to trim out the electrical and build my furniture. All the wire stub outs on the back wall are going to light up my cabinets. 6 Detlof and 6 Ekets, Billy corner and a built in.
20220408_155220.jpg
20220408_155225.jpg
20220408_155239.jpg
20220408_155258.jpg
 